Hai Phong 1 Coal-Fired Power Plant

power

Cost

$0.6b
$640,000,000

operational

2011

Capacity

1k
MW Electricity

Description

Construction of a 600 MW coal-fired power plant comprising two 300 MW units in Hai Phong. A Marubeni–Dongfang Electric consortium supplied the EPC works, while project finance included a China Eximbank buyer's credit, Japanese finance, a Vietnamese bank loan and sponsor resources.

Finance

logo
$278m loan
Exim Bank of China
Development bank

Contractors

Governing authorities